Multiplex & Rockingham Park JV
The Leighton Apartment commenced in January 2010 with completion in August 2010.
The project was completed eight weeks ahead of schedule and on budget to an extremely high quality of finish facilities include a lap pool, gymnasium and common area facilities. The project was a negotiated design and construct contract for 45 apartments over four levels overall including one level of basement with hard limestone digging. The building is extremely close to the beach thus special consideration was given to construction activities and material selection in the coastal environment.